Director Project Updates

s

Project Overview

Project Gallery

11/4/2024

Stage two tile work will begin after-hours on Tuesday, November 12. This stage will include the replacement of the interior mosaic. Installation is scheduled to continue through Friday, November 15. Access to the main entry and meeting rooms will not be impacted, and access through the main hallway will be temporarily confined to 3 feet on either side of the mosaic. Thank you for your continued patience with our interior work. Once this stage is over, we will move on to replace the entryway carpet walk-off mats. As always, we welcome your input or questions.

10/22/2024

The Main Entrance will remain closed until Friday morning (October 25) for full concrete curing.

On Wednesday (October 23), crews will be working outside putting topsoil in the gaps near the front entrance.  This may continue into Thursday. Inside, the construction crew will be working on the tile base. The tile work for stage one should conclude by the end of Wednesday.

10/18/2024

Thank you for your patience during the main entrance closure this week! We appreciate your understanding as we’ve navigate these needed repairs. We’re nearly ready to reopen the main entrance. While removing the old sidewalk, we discovered that the original base layer was sand, instead of the recommended rock, which likely caused the cracking over time. The contractors have been preparing the area for our new sidewalk, and the cement is scheduled to be poured on Monday, October 21. If all goes as planned, we anticipate reopening the main entrance on Wednesday, October 23, one day later than originally planned).

Please note that the Library will be closed on Monday, October 21, for a staff development day, with a delayed opening at 1 p.m. opening on Tuesday, 10/22. However, drive-thru window services will remain open at 9 a.m on Tuesday, 10/22.

Tile work will also continue on Monday. Although we had hoped to preserve the mosaic tile, the removal of the green border tile revealed issues with cracking and instability throughout, leading to the decision to replace all the tile. Fortunately, our contingency budget covers this additional work, but it does mean that tile work will extend for at least another week. It should not impact any meeting rooms or entrances.

10/18/2024

Thank you for your patience during the main entrance closure this week! We appreciate your understanding as we’ve navigate these needed repairs. We’re nearly ready to reopen the main entrance. While removing the old sidewalk, we discovered that the original base layer was sand, instead of the recommended rock, which likely caused the cracking over time. The contractors have been preparing the area for our new sidewalk, and the cement is scheduled to be poured on Monday, October 21. If all goes as planned, we anticipate reopening the main entrance on Wednesday, October 23, one day later than originally planned).

Please note that the Library will be closed on Monday, October 21, for a staff development day, with a delayed opening at 1 p.m. opening on Tuesday, 10/22. However, drive-thru window services will remain open at 9 a.m on Tuesday, 10/22.

Tile work will also continue on Monday. Although we had hoped to preserve the mosaic tile, the removal of the green border tile revealed issues with cracking and instability throughout, leading to the decision to replace all the tile. Fortunately, our contingency budget covers this additional work, but it does mean that tile work will extend for at least another week. It should not impact any meeting rooms or entrances.

10/11/2024

We’re nearing the end of the fall construction phase, and we greatly appreciate the support of our staff and community.

  • Sitework Complete: After addressing unexpected groundwater, sitework is finished.
  • Front Canopy Painting: Resumed on October 7. Final punch list items are in progress.
  • Sidewalk Replacement: Starting October 15, the sidewalk under the front canopy will be replaced, causing main entrance closure from October 15-21. Loudest work (demolition) is expected on October 15-16. Main entrance will reopen October 22.
  • Alternate Entrances: During this closure, use Meeting Room A or the Children’s Room (Family & Handicap Access). A temporary ramp will be available.
  • Tile Work: Demolition work began today and will be ongoing during off-hours. Tile installation starts October 16 and will continue while the library is open. Meeting rooms remain accessible, and bathroom access will be maintained. Storytimes next week will be moved to YMCA.
  • Library Closed: On October 21 for staff development and bathroom tile work. Reopens October 22 at 1pm. Drive-thru window services will remain open.

Thank you for your patience as we complete these final steps!

10/4/2024

Thank you for your continued patience as we approach the finish line—just a few more weeks before we pause work for the winter.

While most of the exterior site and drainage work is complete, a few final punch list items remain. Here’s what to expect in the coming weeks:

  • Painting on the front entry canopy will resume on October 7, following a brief pause for the book sale.
  • Concrete work for the sidewalks will begin on October 11. We will be replacing the sidewalk under the front canopy and adding a new sidewalk connecting to the Multipurpose Room door.
  • The main entrance will be temporarily closed starting October 15. Please use Meeting Room A (Main Entry) or the Children’s Room (Family & Handicap Access) during this time.

Interior tile work:

  • Tile demolition will occur while the library is closed.
  • Tile and grout installation is scheduled for October 15-22, while the library is open.
  • We plan to complete the bathroom tile work on October 21 (Staff Development Day, library closed) and will open later on October 22 (1-8pm).

We understand this phase may be more disruptive. Foot and vehicle traffic will be rerouted with cones and signage to guide you. If you’re attending a program or using our meeting rooms, please be aware of potential construction noise. We’ll do our best to limit loud work to off-hours.

Bathroom access will remain available during open hours.

Please reach out with any questions or concerns:
Email: director@eglibrary.org
Phone: 518-477-7476

Thank you again for your understanding!

9/25/2024

Progress! Site work and painting are the main focus this week, which includes storm drainage work and the restoration and seeding of top soil.

Painters are diligently prepping and painting the exposed steel and underside of the entry and drive-thru canopies, alongside the concrete canopy base. The exposed steel, currently in white and maroon, is being transformed to a charcoal grey and white, aligning with the new color scheme for the windows and front entry door, which will replace the current green with charcoal grey.

We invite you to check out our updated project gallery video to see the work in action.

Please note that the drive-thru will be closed from 6am to 4pm on Wednesday 9/25, Thursday 9/26, Friday 9/27, and Monday 9/30, although the library will remain open, and returns and holds can be picked up at the circulation desk. For those with mobility challenges, feel free to contact the library at 518-859-6251 for curbside service. Thank you for your continued patience.

9/16/2024

This week our contractors will be focusing on site preparation and painting all exterior metal doors and the metal around entry canopies. Today, the began the process by sanding the doors, which can be quite noisy!

Please note that doors with windows will be replaced during the upcoming spring window replacement project. While we aim to minimize the disruption, some aspects of this work- such as noise, debris, changes to parking, and foot traffic- may affect your visit to the library.

We will continue to provide construction updates online, although please be aware that scheduled work may change without prior notice. If you have any concerns about how this may impact your visit, meeting, or program, please don’t hesitate to contact us at 518-477-7476.

Thank you for your understanding and patience as we carry out these essential building renovations.

9/10/2024

The construction project committee is working on finalizing finishes. Tile and grout have been selected, and finishes on the exterior EIFS, metal trim, metal doors and metal windows are under consideration. Site work continues and this week’s priorities include:

  • Test pit for utilities
  • Storm drainage installation
  • Blacktop repair at the parking lot storm inlets

9/3/2024

Construction work begins today! The library will remain open for the duration of the project with minimal public disruptions.

  • Construction hours will typically take place between 7:30 am-4:00 pm
  • A fenced staging area will be located in the rear parking lot
  • The first step will be to remove hazardous trees (several dead trees in rear of building)
  • Drainage work will begin in the grassy area along Community Way

 

In 2023, the library engaged Hyman Hayes Associates to complete a Building Conditions Survey. The survey aimed to assess the current state of the library facility and devise a five-year plan for Capital Project needs.

 

Phase 1 Capital Improvements

1. Exterior Envelope Renovations

  • Upgrading the Exterior Insulation Finishing System (EIFS) with new mesh, finish coat, and sealants
  • Conducting envelope improvements to prevent water intrusion, ensuring the building’s structural integrity and safety
  • Installation of a new drainage system around the perimeter of the building, including swails, catch basins, PVC pipes and regrading of the areas surrounding the building to eliminate water entry routes along the foundation
  • Removal of trees that impede the ability to complete the EIFS work, as well as trees that are are a safety concern

2. Main Entryway, Windows, and Drive-Thru Window Entry Renovations

  • Installing new LED light fixtures, enhancing energy efficiency
  • Replacing the gypsum board ceiling in the entryways to maintain structural integrity and aesthetics
  • Refinishing the metal breezeways and fabric canopy to improve appearance and durability
  • Replacing existing concrete entry sidewalk
  • Repair and paint exterior metal doors
  • New windows to replace current leaking storefront windows

3. Interior Tile Work

  • Addressing safety issues by replacing tile in the main lobby area
  • Removing non-functioning magnetic book security scanner gates that hinder accessibility and flexibility of space

 

Phase 1 Construction Project Team

Name Title Organization
 Bruce Doyle  Senior Project Manager  Wainschaf Associates, Inc.
 Charlie Pensabene  Vice President, Board of Trustees  East Greenbush Community Library
 Dawn Geurds  Business & Operations Manager  East Greenbush Community Library
 Jay Stasack  Senior Associate  Hyman Hayes Associates, LLC
 Jenna Schmonsky  Administrative Assistant  East Greenbush Community Library
 Jill Dugas Hughes  Director  East Greenbush Community Library
Josh Wainman  President  Wainschaf Associates, Inc.
We welcome community feedback and questions. Please contact Jill Dugas Hughes, Director, (518) 477-7476, director@eglibrary.org.

Phase 2 Capital Improvements

  • Roof Replacement

Phase 3 Capital Improvements

  • Public Bathroom Renovations
Subject East Greenbush Card UHLS Card UHLS MyCard
Library Card Registration Free to any individual who resides or pays taxes in the East Greenbush Community Library taxing district or Town of Schodack. Cards expire and must be renewed every three years.

Free to any individual who volunteers or works at the EGRN Library. Cards expire and must be renewed yearly.

Free to partner educational agencies with verified employment. Cards expire and must be renewed yearly.

Those that live outside the UHLS area may purchase a temporary card at the price established by our Table of Fines and Fees. Cards expire and must be renewed yearly.

All ages eligible. Youth under age 16 must have their application completed and signed by a parent or guardian, who provides acceptable identification for them.

Card blocked at $5 or more in replacement costs or fines/fees

Fines vary according to individual library rules and UHLS resource sharing rules. The EGRN Table of Fines and Fees are applicable for items which are checked out from the East Greenbush Community Library

Free to residents residing in a community served by a UHLS library.

All ages eligible. Youth under age 16 must have their application completed and signed by a parent or guardian, who provides acceptable identification for them.

UHLS library cards expire and must be renewed every three years.

Card blocked at $5 or more in replacement costs or fines/fees

Fines vary according to individual library rules and UHLS resource sharing rules. The EGRN Table of Fines and Fees are applicable for items which are checked out from the East Greenbush Community Library

The UHLS MyCard is a fine-free, limited-access library card for youth. It is intended to address multiple barriers to serving youth and families, including:

  • Barriers to access related to fines (e.g. computer access, checking out materials)
  • Parents not present for a child’s library card registration
  • Previous fines on a child’s card

Free for youth residing in a community served by a UHLS library.Applicants 18 and under who are applying for a limited use, UHLS Youth Only MyCard, need to provide name, address, and date of birth.UHLS library cards expire and must be renewed every three years.Youth ages birth to 18 can register unaccompanied, or with the help of a caregiver or relative who is not the child’s parent/guardian.This card may be used at all UHLS Libraries except for the Colonie Town Library.

Card blocked at $10 or more in replacement costs.

No fines for late items

Limits on # of Materials Borrowed Unlimited checkouts Unlimited checkouts Limited total items: Can only have 3 items checked out on their card at a time
Types of Items All eligible item types. All eligible item types except Museum Passes, ILL, and Hot off the Press. Active paid members of the Friends of the East Greenbush Community Library have access to all lending collections. Only items eligible to be borrowed are books (any age level), juvenile and young adult (teen) audiobooks, and juvenile and young adult (teen) DVDs.
Databases/Digital Content EGRN and UHLS subscription databases and digital content UHLS subscription databases and digital content Only items eligible to be borrowed are books (any age level), juvenile and young adult (teen) audiobooks, and juvenile and young adult (teen) DVDs.