We’re thrilled to share that all windows are installed and the EIFS work is officially complete! The finishing touches are almost done- this includes the entryway carpet, entryway doors, and a few minor details on the interior window sills. Phase 1 is nearing completion and have already begun moving towards Phase 2 where we plan to replace the flat membrane roof. We received preliminary notice of initial approval for a construction grant for 66% of the total anticipated project cost ($387,615). There are several more stages before the grant award is official. Additionally, we are working with Assembly Person John McDonald’s office on securing funding for Phase 3.