The proposed 2027 budget maintains current library access and services, responds to operating-cost changes, supports the staff needed to deliver those services, and continues responsible planning for the building and infrastructure.
Public hearing: Tuesday, October 13, 2026, 6:00 p.m. Board approved for community presentation September 28, 2026.
What the proposed levy means for taxpayers
- 2027 East Greenbush proposed tax levy: $2,153,060
- Increase from 2026: $72,810 (3.5%)
- Estimated tax rate: $0.7264 per $1,000 assessed value
- Estimated annual increase for a $300,000 property: $6.84
| Assessed value | Estimated 2027 annual library tax | Estimated annual increase | Estimated monthly increase |
|---|---|---|---|
| $250,000 | $181.60 | +$5.70 | +$0.48 |
| $300,000 | $217.92 | +$6.84 | +$0.57 |
| $400,000 | $290.56 | +$9.13 | +$0.76 |
Estimates use the proposed 2027 levy and current taxable assessed value. Individual tax bills may vary based on final assessment data and applicable exemptions.
What this budget maintains
The proposal is designed to maintain the library access and services residents use today.
- Open seven days a week
- Books, eBooks, audiobooks and digital resources
- Programs for children, teens, adults and families
- Public computers, Wi-Fi, printing and technology help
- Meeting rooms and community spaces
- Outreach and community partnerships
- Drive-through service
- Assistance from library staff
What is driving the 2027 change
| Area | Explanation |
|---|---|
| Personnel and required benefits | Salary budget +6.0%; benefits +8.9%. The salary budget includes a 3.5% cost-of-living adjustment, scheduled steps, targeted equity adjustments, and normal vacancy and hiring changes. |
| Collections, programs and technology | Maintains current service levels, including materials, digital resources, programs, public technology, and related systems. |
| Building and operating expenses | Non-personnel operating costs decrease 0.9% overall while routine building and operating needs are maintained. |
| Revenue and contractual assumptions | Use of prior/restricted funds drops sharply. The Schodack service contract remains under discussion; the proposed budget assumes $500,000. |
Community use remains strong
Selected 2025 measures compared with 2024 actuals:
- Library visits: +14%
- Overall program attendance: +22%
- Summer Reading event attendance: +35%
- Registered borrowers: +16%
- Digital content circulation: +7%
- Outside group meeting-room use: +27%
These measures show the level of community use the proposed budget is intended to sustain.
The overall budget picture
| Budget category | 2026 amended | 2027 proposed | Change |
|---|---|---|---|
| Income | $2,672,750 | $2,789,060 | +4.4% |
| Fund balance and restricted funds used | $205,645 | $45,000 | -78.1% |
| Operating expenses | $2,581,430 | $2,708,031 | +4.9% |
| Transfer to capital reserves | $296,965 | $126,029 | -57.6% |
| Total appropriations | $2,878,395 | $2,834,060 | -1.5% |
Total appropriations are $2.834 million, 1.5% lower than 2026 because the planned transfer to capital reserves is lower. Operating expenses increase 4.9%, while reliance on fund balance and restricted resources declines substantially.
Fiscal stewardship
- Use of fund balance and restricted funds falls from $205,645 to $45,000, reducing reliance on prior-year resources.
- Non-personnel operating costs decrease 0.9% while current service levels are maintained.
- Major capital work is planned separately and supported by reserves, grants, insurance proceeds when available, and outside funding.
- Contracts, operating costs, and outside funding opportunities are reviewed as part of the annual budget process.
- The proposed 2027 transfer to capital reserves is $126,029 for future building and infrastructure needs.
Planning for the building's future
Capital needs are tracked separately so uncertain or one-time projects do not appear as routine operating expenses.
| 2027 planning item | Estimate | Outside funding identified | Current library planning amount |
|---|---|---|---|
| Public bathrooms including bottle filler | $381,405 | $250,000 grant | $131,405 |
| Parking lot: restriping, seal coating, ADA spaces | $40,000 | None identified | $40,000 |
Possible moisture or slab condition
Still under investigation. The $250,000 amount is a planning allowance to evaluate potential financial exposure if work is ultimately found necessary. No final scope, responsibility, funding source, or cost has been determined.
Longer-term needs identified in the capital plan include Community Way, staff spaces, space planning, technology/AV improvements, flooring and furnishings, and major building systems.
Where the money comes from and where it goes
| 2027 proposed resource | Amount |
|---|---|
| East Greenbush tax levy | $2,153,060 |
| Schodack service contract* | $500,000 |
| Gifts and grants | $66,000 |
| Interest and library charges | $63,500 |
| Other public aid | $6,500 |
| Prior/restricted funds used | $45,000 |
| 2027 proposed use | Amount |
|---|---|
| Personnel | $2,097,591 |
| Other operating costs | $610,440 |
| Capital reserve contribution | $126,029 |
*The Schodack service contract remains under negotiation. The proposed budget assumes $500,000.
Budget proposition and voting information
Proposition: Shall the 2027 Library budget in the amount of $2,834,060, as proposed by the East Greenbush Community Library Board of Trustees, be approved?
- Date and hours: Monday, November 16, 2026, 9:00 a.m.–8:00 p.m.
- Location: East Greenbush Community Library, 10 Community Way
- Eligibility: Eligible East Greenbush voters may participate.
- Trustees: Two trustee seats are also scheduled to appear on the ballot.