Titan Roofing is scheduled to return the week of July 20 to complete installation of the metal roof trim and roof ladder. Work will occur between 5:00 a.m. and 8:30 a.m. on the front of the building before moving to the rear each day to minimize disruption to library...
Work on the roof replacement project is temporarily on pause. The new rubber roof has been installed, and we are currently waiting on the delivery of metal materials needed to complete the finishing work.
The Children’s Room reopened this week with refreshed carpet and an updated layout, and it looks great! Other than a few remaining punch-list items (including ceiling tiles), the Children’s Room carpet replacement project is now complete. Children’s Room New...
Interior renovations in the main part of the library are nearly complete, with new carpet installed and most collections available again. Beginning Monday, May 18, renovation work will move into the Children’s Room and Playroom. These areas will be closed to the...
We’re heading into a busy week as renovation work continues. There may be some disruptions, but we’re making steady progress toward a refreshed library. Moving, carpet, painting, and roof work will take place this week. What to Expect Inside Most collections partially...