We’re nearing the end of the fall construction phase, and we greatly appreciate the support of our staff and community.
- Sitework Complete: After addressing unexpected groundwater, sitework is finished.
- Front Canopy Painting: Resumed on October 7. Final punch list items are in progress.
- Sidewalk Replacement: Starting October 15, the sidewalk under the front canopy will be replaced, causing main entrance closure from October 15-21. Loudest work (demolition) is expected on October 15-16. Main entrance will reopen October 22.
- Alternate Entrances: During this closure, use Meeting Room A or the Children’s Room (Family & Handicap Access). A temporary ramp will be available.
- Tile Work: Demolition work began today and will be ongoing during off-hours. Tile installation starts October 16 and will continue while the library is open. Meeting rooms remain accessible, and bathroom access will be maintained. Storytimes next week will be moved to YMCA.
- Library Closed: On October 21 for staff development and bathroom tile work. Reopens October 22 at 1pm. Drive-thru window services will remain open.
Thank you for your patience as we complete these final steps!