Thank you for your continued patience as we approach the finish line—just a few more weeks before we pause work for the winter.

While most of the exterior site and drainage work is complete, a few final punch list items remain. Here’s what to expect in the coming weeks:

  • Painting on the front entry canopy will resume on October 7, following a brief pause for the book sale.
  • Concrete work for the sidewalks will begin on October 11. We will be replacing the sidewalk under the front canopy and adding a new sidewalk connecting to the Multipurpose Room door.
  • The main entrance will be temporarily closed starting October 15. Please use Meeting Room A (Main Entry) or the Children’s Room (Family & Handicap Access) during this time.

Interior tile work:

  • Tile demolition will occur while the library is closed.
  • Tile and grout installation is scheduled for October 15-22, while the library is open.
  • We plan to complete the bathroom tile work on October 21 (Staff Development Day, library closed) and will open later on October 22 (1-8pm).

We understand this phase may be more disruptive. Foot and vehicle traffic will be rerouted with cones and signage to guide you. If you’re attending a program or using our meeting rooms, please be aware of potential construction noise. We’ll do our best to limit loud work to off-hours.

Bathroom access will remain available during open hours.

Please reach out with any questions or concerns:
Email: director@eglibrary.org
Phone: 518-477-7476

Thank you again for your understanding!